One file for fifty sites: how a multi-site assignment works

Dozens of locations across several airspace zones, delivered in one structure. How we plan, request permissions and deliver.

By Anton De Vis, Founder and pilot4 min read
Contents of this article
  1. Step 1: the list becomes a file
  2. Step 2: each site gets an airspace status
  3. Step 3: sites become flight days
  4. Step 4: requesting permissions, with reserve dates
  5. Step 5: the flight day
  6. Step 6: one delivery
  7. What this requires from you as a client
  8. Limits

A property manager with a portfolio of branches wants a current aerial image of each site, in the same quality and the same file structure. Photographing one site is simple. Fifty sites spread across the whole country is a planning assignment with a drone in it.

This article describes how we approach such an assignment, based on a recent assignment with 50 retail sites in Flanders, Brussels and Wallonia.

Step 1: the list becomes a file

The assignment starts with a list of addresses. That list is rarely free of errors. Ours had 52 rows for 50 unique sites: two addresses appeared twice. That is one flight with two deliveries, not two flights.

Each site gets a record with coordinates, a code, access, surroundings and the required images. That record follows the site until delivery.

Step 2: each site gets an airspace status

We check the geozones for each site. In this assignment, about half were outside any zone. The other half were spread over six zones: the CTRs of Brussels, Antwerp, Ostend and Charleroi, the zone around Kortrijk-Wevelgem and a military zone. One site was on the edge of a port area with its own application procedure.

We also note the edge cases: a site 500 metres from a prison, a site just outside a zone boundary, a site along a canal where we do not fly over the water. These edge cases also determine the order and the time of day on the flight day.

Step 3: sites become flight days

With the airspace status and the addresses, we build flight days. Three rules:

  • Group by region and by zone. Sites in the same CTR on the same day limit the number of applications.
  • Busy places first. We fly shopping streets and town centres early in the day or at the weekend, when there are the fewest people.
  • Real driving times, not the distance as the crow flies. We optimise the order for each day based on the actual route. A twelve-hour flight day needs a margin for weather and unforeseen situations.

In this way, 50 sites became a handful of flight days, each with a departure time, a sequence and an expected end time.

Step 4: requesting permissions, with reserve dates

For sites in a CTR, we request permission from skeyes, with a minimum lead time of 8 days in VLL1 and 15 days in VLL0. For the military zone, the port area and the other zones, we follow their own procedure. For every site with a long lead time, we immediately request a reserve date as well.

That proved necessary. Part of the planning had to shift. Because the reserve permissions were already in progress and each new application was set against its own deadline, the assignment could continue without any site having to wait for a completely new lead time.

Step 5: the flight day

For each site, the pilot follows the same routine: arrival, check of the surroundings, flight, check of the images on site, departure. Where necessary, he calls the control tower 30 minutes beforehand and reports take-off and landing. In zones with many people, he works with an observer.

The images are checked for each site before he leaves. Revisiting a site because an image is out of focus costs half a day and sometimes a new application.

Step 6: one delivery

Each site is delivered with the same file names, the same image angles and the same quality control. The client can compare the sites side by side without searching for which file belongs to which branch. During the assignment, the status of each site is visible: planned, requested, flown or delivered.

What this requires from you as a client

  • A correct list: address, coordinates if you have them, and a contact person per site
  • Permission from the owner or manager of each site
  • A window, not a fixed day: a period of a few weeks allows planning around weather and application lead times
  • One point of contact for questions during execution

Limits

HOVVR works with one pilot. We plan a portfolio of fifty sites over several flight days. If dozens of sites must be flown on the same day, or if the assignment requires the contracting authority's own quality system, a larger firm is a better choice. We say so beforehand.

Read also: Permission in a CTR: what the application lead time means for your planning

ShareShare on LinkedIn
profile_photo_anton_devis

About the author

Anton De VisFounder and pilot

I have been flying drones for more than ten years. We hold an operational authorisation in the Specific category based on a SORA risk assessment, for higher-risk flights such as those in urban environments.

  • Certification: EASA Open A1/A2/A3 + EU-STS
  • Authorisation: Specific category, operational authorisation based on SORA
  • Flying experience: 10 years

Quote request

Tell us which building it is and what you will use the data for

Archiving, restoration, measurement and public outreach each require a different level of detail. Based on the building and the intended use, we propose the right resolution and delivery.

  • Location
  • Estimated area
  • Desired output
Request a quoteAsk your question first