A large part of Flanders and Brussels lies within the controlled zone of an airport. A drone flight there requires prior authorisation, and that authorisation has a fixed minimum lead time. This is often why a client hears that a flight can only take place "in two weeks", even though the weather is perfect tomorrow.
This article explains how it works, based on a recent assignment with fifty locations spread over six airspace zones.
What a CTR is
Around the airports of Antwerp, Brussels, Charleroi, Liège and Ostend lies a control zone (CTR). The lower airspace within it is managed by skeyes, the Belgian air traffic control. For drones, this zone is divided into three levels, based on the distance to the runway:
| Zone | Location | Request at the latest |
|---|---|---|
| VLL0 | Above and right next to the runways | 15 days in advance |
| VLL1 | Above and near the airport | 8 days in advance |
| VLL2 | Further from the airport | 3 hours in advance |
Around Kortrijk-Wevelgem, a similar division into two zones applies. Military zones, such as around Beauvechain, and port areas, such as around North Sea Port, each have their own procedure and lead times.
A request is submitted via the skeyes DAA application. The lead time is a minimum: skeyes needs that time to coordinate the request with the air traffic controllers and other parties involved. A request that arrives too late is not processed.
What happens after approval
An approved request is not yet a flight permit. Two more steps follow:
- Confirmation. In VLL0 and VLL1, the pilot must confirm between 1 day and 3 hours before the flight that it will go ahead. In VLL2 this happens automatically.
- Contact with the control tower. In VLL0 and VLL1, the pilot calls air traffic control 30 minutes before take-off. At that point, they can still postpone or restrict the flight, for example in case of heavy air traffic.
During the flight, the pilot reports take-off and landing in the application.
Why this determines your schedule
The lead time is fixed. The weather is not. Suppose a site is in VLL1 and the desired flight day is ten days away. Then the request has to be submitted today. If it is too windy on that day, there is no new date tomorrow: a new request again needs 8 days.
In the assignment with fifty sites, fourteen were in the Brussels CTR, five in the Antwerp CTR, two in the Ostend CTR, one in the Charleroi CTR, two in the Kortrijk zone, one in a military zone and one on the edge of a port area. The rest were outside any geozone. Three things made the difference:
Request backup dates right away. For every site in VLL0 or VLL1, we requested a backup date in addition to the planned day. When the weather made a flight day impossible, the authorisation for the new date was already in place.
Group sites by zone and by day. Flying sites in the same CTR on the same day limits the number of requests and confirmations. We schedule city centres early in the day or at weekends, when fewer people are on the street.
Clarify edge cases in advance. A site 500 metres from a prison, a site just outside a zone boundary, a quay along a canal. These are not problems if you spot them before planning. They do become problems if you discover them on the day of the flight.
What you can do as a client
- Ask early. The sooner we know the address, the sooner we see whether a request is needed and how many days it requires.
- Give a window, not a day. "Sometime in week 42" is easier to plan than "Tuesday", especially in a CTR.
- Report hard deadlines immediately. If the imagery is needed for a construction meeting or an insurance deadline, we plan backwards from that date.
A location without a geozone is usually planned within 5 to 10 working days. In VLL1, count on at least 8 days, in VLL0 on at least 15. This is also stated in your quote, together with the zone in which your site is located.